Cable loading on in good order.The cable will connect Europe.

To the world's top level as the goal, the obstacles

Highly attention of the world's progress

In June 2017, from ibaraki prefecture Hitachi port has a large cargo ship at sea.The ship loaded with laying between Britain and Belgium, 118 km of power cable, the total weight of 5200 t."Manufacturing cable takes about 1 year time, but this is the world's first product, so only success, not failure.We always will ensure the quality in the first place "this technical project leader give zhe said.Cable in late July to Britain, undertake ocean bottom construction from the beginning of August.

Sean phillips, head of the laying construction was an engineer
Sean phillips, head of the laying construction was an engineer

During the construction of the laying of submarine cables, there are many uncertain factors.Before laying submarine survey, for example, it was found that the first and the second world war the remaining five mines, therefore the demining operations.In addition, due to the tourist season in Belgium and Britain's environmental regulation season season and location factors, such as in to shore is limited by a larger place allow homework time.During the operation, climate factors may also lead to cannot work.This project was completed in January 31, 2019, "despite the uncertain risk factors, but in order to avoid delay, we must advance the homework carefully plan" set operation director Sean phillips said.

The project team now for 25 people.Britain, Belgium, the Netherlands and Ireland and other experts gathered of each nationality.As a professional football team.Responsible for ruling over the scene laid homework kawaguchi hui says: "only when each character give full play to their abilities, to play out the power of the team.I think that the use of partial optimization at the same time, to pursue the overall optimization - which is the key to project success."

Deputy project manager hart, bandar Haydn
Deputy project manager hart, bandar Haydn
Project engineer, Catherine barker
Project engineer, Catherine barker

Project members of "feeling"

Team members to a common feeling, is to be able to participate in the project of joy.

Deputy project manager hart, bandar Hayden said: "such a huge project, involving capital and related personnel is very confused.Process is also very complex.But if we can successfully complete the project, as a technical personnel must be confident."In addition, the project engineer Catherine buck also excitedly said:

"Work, there will be and manufacturing cable factory employees opportunities to work with Japan.Countries, work steps and project the necessary data is also different, sometimes I think at this point to be very difficult to understand each other.But, can overcome these difficulties, as a member of the submarine cable project with the use of new technologies and struggle, I feel very proud."

Sumitomo electric group in the UK - the Belgian multinational connecting cable in the project bidding, to Europe's electric power industry has brought the huge impact.Now in Europe in the electric power industry, sumitomo electric group's reputation has been no one know, no one knows all.As market participants to gain a foothold, it is of great significance.Not only the power industry, both in Britain and Belgium's government is also very concerned about the progress of the construction.

"In January 2019.If this project can be completed smoothly, the social from all walks of life to our evaluation will be to the next level.If completed the world's first high voltage 400 kv dc described.properties of cable laying, for us, this is a major achievement.Based on this, if you can through the project of European solutions to social issues, offer some help, we will feel honored.We hope that the future can also to the power of technology and talent sumitomo electric group maximize, contribute to the world ".

The line of sight of ancient bridge, is aimed at the next project.

Inform the construction summary of the sign
Inform the construction summary of the sign
Inform the construction summary of the sign
Kawaguchi hui Ming (for the third front left) is responsible for the local laid with construction team.In Japan as the core, the experts from across Europe together
Kawaguchi hui Ming (for the third front left) is responsible for the local laid with construction team.In Japan as the core, the experts from across Europe together